Cookeville officials advancing a proposed 9.4-acre annexation along Goodwin Road despite sewer capacity restrictions that currently limit development.
Cookeville Community Development Director Jon Ward said the City Council recently approved a resolution sending the proposed plan of services to the Planning Commission. Ward said improvements to the Cane Creek pump station are already underway.
“So we anticipate that, you know, it may be 18 months and the capacity would be there to move forward with the whole development,” Ward said, “So that’s why there was a limitation that was provided by our water quality control department relative to sewer capacity.”
Ward said the Water Quality Control Department can currently accommodate only four additional homes on the property. However, Ward said those restrictions would not necessarily prevent annexation from being approved before the pump station upgrades are completed.
“There were some comments provided in our preliminary draft of the plan of services where there were limitations on the number of units they were willing to serve at this time, right?” Ward said. “But, you know, likely the improvements move forward and the capacity would be there by the time he even needed it, right?”
Ward said the pump station improvements have been planned for several years to accommodate growth in that area of Cookeville. The project was already progressing through design before the Goodwin Road annexation request, and similar sewer restrictions have affected other proposed developments.
The property owner requested annexation to obtain city water, sewer, police and fire services. Ward said the tract is already bordered by Cookeville city limits on three sides, and the owner could initially develop four homes if the necessary approvals are granted, with additional construction possible once sewer capacity increases.
The Planning Commission will study the proposal in November and could make a recommendation in December. Ward said the proposal would then return to the City Council after the first of the year, with public hearings required before final annexation approval.
“The planning commission will include it on the agenda for them to take for study in November and they can act on it in December and that will be their recommendation to the council and then it will go back to council after the first of the year,” Ward said.