Cookeville plans to widen another section of Green Gate Lane, adding sidewalks and street lighting near the Hampton Creek Apartments.
Community Development Director Jon Ward said the city has negotiated an agreement with the owners of Hampton Creek Apartments for approximately 26 feet of permanent easement. The project would extend the existing three-lane roadway near Willow Avenue Church of Christ to the apartment complex entrance.
“So that would widen the street, add an additional lane, sidewalks, street lighting, a water line would have to be relocated as part of this project as well,” Ward said. “And we have the easement continuing to the east, that would allow for future improvements of that facility.”
Ward said the agreement follows more than six months of negotiations with the apartment property owners to improve the area around the new Target/Home Depot. The owners preferred granting an easement rather than selling the property outright because of their financing arrangements.
Ward said the city would be responsible for lender fees, attorney fees and recording costs associated with the agreement. Ward said those expenses are not expected to exceed $10,000.
Ward said the permanent agreement would accommodate gas, water and sewer infrastructure without requiring separate easements.
City officials are also discussing a possible redesign where Miracle Road meets Green Gate Lane. The proposal would extend the curve to create a continuous roadway rather than requiring drivers to make a full stop.
A preliminary design exists for that intersection, but discussions with Willow Avenue Church of Christ are ongoing.
The widening project could begin as early as spring or summer 2027. The Cookeville City Council is scheduled to consider the easement agreement Thursday.