Deteriorating electrical equipment at the Clay County Schools central office threatens district operations and could force the school board to postpone planned capital improvements.
Maintenance Supervisor Matt Sidwell said the building’s original electrical system has become increasingly unreliable. Officials have temporarily stabilized the equipment, but another failure could have consequences beyond the central office.
“And what we get into is, if when we lose if something big happens and this falls out, we lose internet,” Sidwell said. “I mean, so we’re in a bad way and that’s what’s running our schools, so we can’t do without that.”
Sidwell said years of exposure to damp conditions have left the electrical panels rusted and increasingly difficult to maintain. School officials reported flickering lights and outages that forced employees to use extension cords between sections of the building.
“And it’s as bad as the wiring is, the boxes,” Sidwell said. “I mean, they are… they’re bad. When you get one off, it’s just hard to explain what it’s like to get one of them fired back up.”
District officials have consulted with Upland Design and Tri-County Electric about possible repairs. Replacement equipment could take approximately six months to obtain, leaving the district facing an extended wait even if the project moves forward soon.
Sidwell said engineers must determine whether a 400-amp electrical service would meet the building’s needs or whether an 800-amp system would be necessary. The decision could also depend on whether the district eventually wants to use the building’s second floor, which currently serves primarily as storage.
The board discussed how an electrical overhaul could affect the district’s capital budget. Officials had hoped to complete paving improvements at Clay County High School this year, but an expensive electrical project could take priority.
“And it might require, if we had to proceed, it might require altering our plans for capital budget in the current year,” Board Chairman Benji Bailey said. “We have a couple paving projects in mind. Last year we were able to repave the SONIKA. Our plan this year was to hopefully do the high school.”
Officials said previous electrical projects at other district facilities cost approximately $130,000 at Hermitage Springs and $300,000 at Celina K-8. No formal estimate has been presented for the central office, although administrators said expediting replacement equipment could cost an additional $50,000 to $55,000.
The project could also require temporarily closing the central office and relocating administrative employees while electrical work is completed. Sidwell said the district has a small generator, but it cannot support the infrastructure needed to maintain school internet operations.
Sidwell said he expects to return to the board in December with more information about repair options. The board took no action Thursday as officials await engineering recommendations and cost estimates.