DeKalb County Commissioners authorized core drilling at the existing downtown jail site for possible construction.

Commissioner Steven Cantrell said the testing will include two properties the county does not currently own. Cantrell said both property owners have granted permission for drilling.

“Instead of a, ‘Well, I’m not sure if it can be built there, it can’t be built there,’ et cetera, et cetera,” Cantrell said, “I would just like to put it to bed one way or the other. It either you can build there or you can’t build there from a engineering perspective.”

Mayor Patrick Ray said the architectural firm Trainer estimated the drilling will cost approximately $30,000. The expense will be paid from the jail construction fund. Commissioners voted 8-6 for the drilling.

“The drilling team has time available after Thanksgiving,” Ray said. “They have indicated a week or two weeks after drilling for some data that will be available.”

Commissioner Andy Pack questioned spending additional money to evaluate the downtown location, citing estimates that construction there could cost 10 to 15 percent more than at the Smith Road site.

Commissioner Greg Matthews said estimates for construction on Smith Road already range from $42 million to $44 million. Matthews said keeping the jail downtown could allow the county to renovate the existing facility for the Sheriff’s Department rather than reducing the number of inmate beds to accommodate office space.

Cantrell said the engineering results could also provide information to prospective buyers of the downtown property should the county ultimately relocate the jail.

Ray said the county has already spent more than $5.3 million on the project since September 2026, including land acquisition and architectural fees. The county is currently paying interest on a $35 million construction loan.

In other business, commissioners unanimously approved five school budget amendments, including more than $54.7 million for new school construction and $42,451 in security grant funding for cameras across the school system. Commissioners also postponed consideration of the Village Market convenience site land lease until December pending answers to questions raised during last week’s workshop.